Showing posts with label Week 6. Show all posts
Showing posts with label Week 6. Show all posts
Sunday, February 21, 2010
The Saga Continues
They are still working on putting in the foundation forms. You can see they are making progress.

Here are more of the forms they still need to put in.
This is the floor plan of our "walk space" (it is a crawl space that you can walk through). You can see all the footings that need to be poured. The pads for columns need to be connected to the rest of the footings.
Thursday, February 18, 2010
More footing work
Wednesday, February 17, 2010
More work on footings
Tuesday, February 16, 2010
A new toilet
They continued putting in forms for the footing today. It is good to see progress every day.
They also redid our plumbing today. They got rid of the old leaky cast iron and concrete pipes. They are going to need to redo our plumbing at least one more time when we get our new septic system. That will be at the end of this project.
I guess the contractor felt bad about us temporarily losing one of our toilets because the house movers put a beam under it. Our contractor brought us a new toilet. It might be inconvenient to use especially in the middle of the night. I guess we could let the workers use it too.
The workers are using one of our outside plug for their tools. Their extension cords have lights on the end to make it easier to find. Now we have little lights under our house.
Monday, February 15, 2010
Started work on the footing
Subscribe to:
Posts (Atom)