Thursday, April 8, 2010

Closer to getting closer to the ground

They have put up all the plywood they are going to before we are lowered to the walls. The current plan is to have the concrete blocks delivered on Friday. The bricklayers will install them on Saturday. The house will be lowered on Wednesday. The plumbing will need to be redone because a lot of it is between the wall and the house. Some of the plumbing needs to be removed to get the beams out after they lower the house.
They also put up the support columns.
Because the concrete blocks need to go up about ten feet to support the fireplace, they installed scaffolding for the bricklayers to use.

No comments:

Post a Comment